🚌 TransportIN PROGRESS Live feed

Lagos–Calabar Coastal Highway (Section 1)

Victoria Island → Lekki, Lagos (Section 1)

First section of the coastal highway along the Atlantic shoreline, from Victoria Island towards the Lekki Deep Sea Port — six-lane rigid pavement with a rail corridor in the median.

Progress40% complete
🎯 Target: 47.5km (Section 1)📅 Due 30 May 2028🕒 Last update 24 Sept 2026

Live from the site

Progress Timeline

Official progress updates alongside verified citizen photos and videos, newest first.

Official Update · 40%24 Sept 2026

Night shifts added; westbound carriageway paving begins.

Citizen Completion Confirmation19 Sept 2026

Drove past the Eleko section on Saturday — the finished concrete stretch is open to site traffic and looks solid.

Video evidence
Official Update · 36%8 Sept 2026

Pavement reaches 7km; median rail corridor pegged out.

Citizen-Reported Issue2 Sept 2026

Diversion around the Akodo works has no signage at night; two near-misses this week.

Official Update · 31%28 Aug 2026

Drainage culverts installed across the Eleko–Akodo stretch.

Official Update · 27%12 Aug 2026

First 3km of rigid pavement laid on the eastbound carriageway.

Official Update · 22%30 Jul 2026

Concrete batching plant commissioned at the Lekki yard.

Official Update · 18%14 Jul 2026

Sand filling completed on the first 6km stretch at Eleko.