🚌 TransportIN PROGRESS

Repair 50km of State Roads

Rehabilitation of key feeder roads connecting Ikorodu, Epe, and surrounding wards.

Progress88% complete
🎯 Target: 50km of roads📅 Due 31 Dec 2026🕒 Last update 30 Aug 2026
No live site feed for this project yet.

Progress Timeline

Official progress updates alongside verified citizen photos and videos, newest first.

Citizen-Reported Issue30 Aug 2026

Visited the Ikorodu axis on 27 Aug — the stretch marked as resurfaced already has cracking and a few potholes forming near the market junction. Worth a quality check before it's marked complete.

Official Update · 88%25 Aug 2026

44km completed. Remaining 6km near Epe junction scheduled for next month.

Official Update · 68%5 Aug 2026

Asphalt laying underway — 30km now resurfaced.

Official Update · 42%12 Jul 2026

Grading and drainage work finished on the first 20km stretch (Ikorodu axis).

Official Update · 12%5 Jun 2026

Project kicked off — site survey and contractor mobilization complete.